DECEMBER 2nd 2019
SHOP is open in new build. COME & SHOP!!
THE BUILD - Autumn 2019
-
CBS August newsletter for a plan outline
-
Week by week progress report on Renovation works.
-
Shop floor plan on Exmoor National Park Planning
December 2nd 2019
SHOP MOVED BACK
NOW OPEN in new build - COME & SHOP!!
Week 1-Sept. 2nd
The way it was
August 29th
The store room Storeroom doorway
.jpg)
.jpg)
Ready to begin
Disconnecting electricity
Builders yard!
Ready to begin
1/16
Weeks 5 and 6
Week 2 - Sept. 9th
Excavated footing 1
Both footings
Glistening cement
Excavated footing 1
1/9
Weeks 3 and 4
All set to strip the roof
Sections of structural roof beam
Insulation above rafters.
All set to strip the roof
1/19
Weeks 7 and 8
Structural engineering under the flat
Cafe exit
End of week 8 'Office' interior
Structural engineering under the flat
1/27
Interior of roadside verge ready for ins
Insulation to side by roadside verge
Office
Interior of roadside verge ready for ins
1/18
Weeks 9 and 10
Plaster boarding 1
Plasterboarding 2
End week 10-Cafe exit. Wc on left.
Plaster boarding 1
1/27
October
Shop moves to village hall
Packing up the shop
Packing up the shop (2)
Weekend success
Packing up the shop
1/18
Weeks 11-13
Cladding is added
Cladding 2
Up on the roof
Cladding is added
1/29